2.2.3 Substructure

We use cookies. Read the Privacy and Cookie Policy

2.2.3 Substructure

As first WTC 2, then WTC 1 collapsed, nearly 600,000 tons of debris fell onto the Plaza level, punching large holes through the Plaza and the six levels of substructure below, and partially filling the substructure with debris. This damage severely compromised the ability of the slabs to provide lateral bracing of the substructure walls against the induced lateral earth pressures from the unexcavated side. This condition was most severe at the southern side of the substructure, adjacent to WTC 2 and WTC 3. In this region, debris from the collapsed WTC 2 punched through several levels of substructure slab, but did not completely fill the void left behind, leaving the south wall of the substructure in an unbraced condition over a portion of its length.

In early October, large cracks were observed along Liberty Street, indicating that the south wall had started to move into the failed area under the influence of the lateral earth pressures. Mueser-Rutledge Engineers were retained to review the situation and make suitable recommendations. As a temporary measure, sand fill was backfilled against the inside face of the south wall to counterbalance earth pressures on the unexcavated side. Following temporary stabilization of the wall, tiebacks were reinstalled through the wall in a manner similar to that used to stabilize the excavation during the original construction of the development. After these tiebacks were installed, it was possible to begin excavation of the temporary sand backfill and the accumulated debris. Tiebacks were similarly installed at the other exterior substructure walls to provide lateral support as the damaged slabs and debris were excavated and removed from the site.